Phase 1 completion is on track within the next 4–8 weeks, with power delivery as the final gating item. The utility company has updated its requirements, now requiring the three-phase power infrastructure — originally planned for Phase 2 and the pond pump systems — to be fully installed before energizing Phase 1. Gas installation is staged and ready to begin immediately upon power sign-off, with an expected completion timeline ahead of the power schedule.